648. The DEEP DRILLER is loaded as shown in the Sample Load Form #5 (Survival), when an unexpected, slowly increasing port list and bow down trim occurs. A leak in C1P is found. By deballasting from ballast tanks 2P and 3P, the inclination slowly decreases. The increase in the longitudinal free surface correction is __________.